MODS:Searched for similar thread on this topic and could not find any so creating a new one. If this is not the right place for this thread please move appropriately, thanks in advance - Regards NPV

Why this thread ?
I've lived most of my life in this area of Bangalore and this is one of the roads I always admired since it used to be one of the finest concreted roads and had lovely, huge trees lining it on both sides. I've seen it transform significantly - stretches near the HAL market being asphalted (on top of the concrete!), potholes suddenly appearing, unending BWSSB, cable laying mess and huge trees being mercilessly chopped (did not get as much attention as Sankey Road). Now road widening seems like it will really happen after all.

Suranjan Das Road (also referred to as the Concrete Road/HAL Road) is a key road that links HAL Aiport Road (more recently also called Old Airport Road) with Old Madras Road (NH4). Important establishments on this road are the HAL market, HAL Hospital on the service road, HAL ground near Jeevan Bima Nagar, BEML, ADE, BWSSB, GTRE, Aeronautical Society of India. Also there is a railway track that runs from the BEML rail coach factory to Byappanahalli railway station to transport the new coaches and other heavy vehicles that BEML produces. This road also has important junctions with Jeevan Bima Nagar and New Thippasandra Main Road. The past 4 years or so there has been talk/reports of this road being widened on PPP basis with Bagmane developers and HAL being the major parties.
The last 6-8 months has seen some progress (if you can call it that!) in terms of trees being felled in quick overnight/weekend operations, laying of BWSSB pipes, cables, etc and now the past week or so more work in terms of actual widening work being carried out. Here is my attempt to give you a sense of what's happening and what could be in store in the coming months.Let's take a tour of the road from Old Madras Road junction towards HAL Airport Road:
1. Stretch from OMR upto GTRE factory - no progress currently but seems like the area beside the railway track will be used for widening. On the other side of the road there is some space beside the HAL office/bus stops which will be used (did not get a picture)
2. Stretch from GTRE factory to C V Raman Nagar entrance near ADE/Michael Palya - seems like the area beside the railway track will be used for widening. On the other side of the road there is the BWSSB campus and heard that they may lose upto 10feet on their frontage (did not get a picture)
3. Stretch from C V Raman Nagar entrance near ADE to C V Raman Nagar entrance near Gitanjali Layout - Seems like the area beside the railway track will be used for widening but in some places is is significantly elevated. On the side is a high boundary wall of ADE and not sure if they will be parting with their land for widening.
Name:  1.CVRN Rlwy Crs twds OMR side1.JPG
Views: 2627
Size:  206.5 KB

Name:  2.CVRN Rlwy Crs twds OMR side2.JPG
Views: 2532
Size:  197.0 KB

Name:  3.CVRN Rlwy Crs Gitanjali Lyt side twds OMR1.JPG
Views: 2834
Size:  171.6 KB

Name:  4.CVRN Rlwy Crs Gitanjali Lyt side twds OMR2.JPG
Views: 2479
Size:  178.8 KB
4. Stretch from C V Raman Nagar entrance near Gitanjali Layout to Gitanjali Layout road - here you can see that the space beside the railway track has been levelled. Hope the service road on the other side is not lost to widening!
Name:  5.CVRN Rlwy Crs Gitanjali Lyt side twds HAL Arpt Rd1.JPG
Views: 2736
Size:  180.9 KB

Name:  6.CVRN Rlwy Crs Gitanjali Lyt side twds HAL Arpt Rd2.JPG
Views: 2459
Size:  182.4 KB
5. Stretch from Gitanjali Layout road to BEML-New Thippasandra Main Road junction - not much space beside the railway track on this stretch so median near service road will go (trees have already been cut down). Again, hoping the service road will not be lost fully ! There was a small park near the service road when nearing BEML. This has been demolished and being levelled now.
Name:  7.Gitanjali Lyt Service Rd Near BEML Corp Off CVRN1.JPG
Views: 2610
Size:  231.4 KB

Name:  8.Gitanjali Lyt Service Rd Near BEML Corp Off CVRN2.JPG
Views: 2421
Size:  170.9 KB

Name:  9.HAL III Stg Svc Rd near BEML.JPG
Views: 2361
Size:  280.7 KB

Name:  10.HAL III Stg Svc Rd near Gitanjali Lyt.JPG
Views: 3338
Size:  208.4 KB

Name:  11.Park  HAL III Stg Svc Rd near BEML1.JPG
Views: 2384
Size:  224.3 KB

Name:  12.Park  HAL III Stg Svc Rd near BEML2.JPG
Views: 2800
Size:  212.0 KB
6. The BEML-New Thippasandra Main Road junction - suddenly this place looks huge, and road is extremely wide, it's just not what it was even 10 days ago ! The BEML two wheeler/cycle stand has gone and made way for a left turn from New Thippasandra Main Road which connects it directly to the HAL III stage service road at the back. Here, the plan is traffic from the BEML junction towards C V Raman Nagar will use the service road and in the other direction traffic will use the 'real' Suranjan Das Road but as you can see signage is not very intuitive so it's confusion all over ! When proceeding from Jeevan Bima Nagar towards C V Raman Nagar also, traffic needs to divert to left and use the service road (this place has been widended but confusing due to bad signage, lack of disipline and enforcement).
Name:  13.ThippasandraBEML Jn.JPG
Views: 2276
Size:  211.4 KB

Name:  14.ThippasandraBEML Jn twds CVRN1.JPG
Views: 2280
Size:  181.4 KB

Name:  15.ThippasandraBEML Jn twds CVRN2.JPG
Views: 2253
Size:  191.3 KB

Name:  16.ThippasandraBEML Jn twds GM Palya HAL Arpt Rd.JPG
Views: 2646
Size:  201.5 KB

Name:  17.BEML Jn twds CVRN1.JPG
Views: 2599
Size:  171.6 KB

Name:  18.BEML Jn twds CVRN2.JPG
Views: 2251
Size:  152.7 KB

Name:  19.BEML Jn twds CVRN3.JPG
Views: 2198
Size:  223.6 KB
7. Stretch from BEML junction to Jeevan Bima Nagar Junction - seems like part of the tree park on one side and part of the HAL ground on the other side will make way for widening
Name:  20.HAL Mrkt twds JBNgr side.JPG
Views: 2776
Size:  178.9 KB
8. Stretch from Jeevan Bima Nagar junction to HAL market - seems like most of the tree park on this side will go, other side has HAL quarters so possible that a few feet on this side will also go.

Hopefully we can get more pictures on this thread along the way to capture the progress, problems, etc

Last edited by Rehaan : 31st October 2013 at 20:48. Reason: As requested
NPV is offline   (3) Thanks Reply With Quote
Old 17th November 2013, 15:33   #2
NPV
Distinguished - BHPian
 
NPV's Avatar
 
Join Date: Oct 2009
Location: Namma Bengaluru
Posts: 4,579
Thanked: 4,279 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

After almost 2.5 years since the work started, there is some progress albeit very slow.

I remember at least 3 occasions on which some local politicos, BBMP folks and contractors have 'commenced' work with banners, some puja, etc.

The progress so far is between the Gitanjali Layout junction and the Micheal Palya junction (between the gates/entry points to C V Raman Nagar).
I heard from an acquaintance that the work is slow due to the decision to widen the road with concrete so that it bonds well with the existing road surface.
Most of the concreting work is complete on the ADE boundary side of Suranjan Das Road.
This work is really "heightening" of the road with concrete

Definitely seems like it will take a long time at this pace to see more significant progress.

Some pictures:
Name:  Srj  1.jpg
Views: 1747
Size:  166.1 KB

Name:  Srj  2.jpg
Views: 1736
Size:  155.8 KB

Name:  Srj  3.jpg
Views: 1749
Size:  187.9 KB

Name:  Srj  4.jpg
Views: 1699
Size:  151.7 KB

Name:  Srj  5.jpg
Views: 1713
Size:  169.0 KB
NPV is offline   Reply With Quote
Old 25th May 2014, 19:10   #3
NPV
Distinguished - BHPian
 
NPV's Avatar
 
Join Date: Oct 2009
Location: Namma Bengaluru
Posts: 4,579
Thanked: 4,279 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

With the road still being widened ever so slowly with small stretches being concreted, this is going to have it's share of mishaps as well, like this one where a Honda Amaze slid off the road partially.
Link
NPV is offline   Reply With Quote
Old 14th September 2014, 20:14   #4
NPV
Distinguished - BHPian
 
NPV's Avatar
 
Join Date: Oct 2009
Location: Namma Bengaluru
Posts: 4,579
Thanked: 4,279 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

The road widening work is still ongoing at various places and still a long way before completion. The stretch near HAL market resembles a war ravaged zone but seems like some work is just starting here since a lot of gravel has been spread out to level the road.
NPV is offline   (1) Thanks Reply With Quote
Old 28th September 2014, 23:55   #5
BHPian
 
anshuman_v's Avatar
 
Join Date: Jun 2014
Location: India
Posts: 207
Thanked: 381 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

This is one long road widening update... I travel on this road every once in a while, and I hope it gets finished soon. School kids and HAL employees, along with office commuters will be saved a lot of hassles once this gets done.
anshuman_v is offline   (1) Thanks Reply With Quote
Old 23rd June 2015, 16:20   #6
NPV
Distinguished - BHPian
 
NPV's Avatar
 
Join Date: Oct 2009
Location: Namma Bengaluru
Posts: 4,579
Thanked: 4,279 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

Quote:
Originally Posted by NPV View Post
The stretch near HAL market resembles a war ravaged zone but seems like some work is just starting here since a lot of gravel has been spread out to level the road.
Recently, I did not observe any progress on the Suranjandas Road work between C V Raman Nagar and Old Madras Road junction.
However, after a very long time I traveled on the other side of the road today and was surprised to see a lot of progress

After the BEML signal, the road is yet to be widened outside the BEML factory campus but just after that, from the HAL Tree Park onwards the work has been completed almost till the end of the road (a small portion still incomplete near HAL Signal).
There is a median separating the lanes which is good news.
The only scary thing is that on the left lane there are some protruding portions of the sidewalk (to accommodate what looked like manholes).
Could prove to be dangerous if one sticks to extreme left and driving/riding fast as it can take you by surprise

This road widening work may qualify for some prestigious award, 4 years and still hardly 50% complete, this for a 2Km stretch!

Last edited by NPV : 23rd June 2015 at 16:26.
NPV is offline   Reply With Quote
Old 27th June 2015, 14:33   #7
Senior - BHPian
 
carwatcher's Avatar
 
Join Date: Feb 2010
Location: Bardez, Goa
Posts: 1,185
Thanked: 995 Times
Default

NPV can't thank you enough for this thread, as I stayed there for 10 years (in Gitanjali Apts.) and moved to other city around 2004.
My sister also told about this road widening working also told me about some recent demolition in Bagmane Tech Park.
But taking such a long time to widen not so long road speaks a lot about our country.
carwatcher is offline   (1) Thanks Reply With Quote
Old 27th June 2015, 20:51   #8
Distinguished - BHPian
 
Rajeevraj's Avatar
 
Join Date: Aug 2011
Location: Bangalore
Posts: 3,168
Thanked: 7,536 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

Wow. Did not know there was a thread for this. NPV, you can probably create a record for the longest time a thread needs to remain active. This widening will go on and on and on.

I frequently use this road and the word that comes to mind is 'aimless'. Apart from proceeding extremely slowly, there seems to be no clear direction for the work. Work happens in patches here and there and then completely stops. Even for the completed sections, there seems to be a lot of other minor things left pending.
Rajeevraj is offline   (1) Thanks Reply With Quote
Old 2nd July 2017, 08:16   #9
NPV
Distinguished - BHPian
 
NPV's Avatar
 
Join Date: Oct 2009
Location: Namma Bengaluru
Posts: 4,579
Thanked: 4,279 Times
Default Re: Suranjan Das Road (Bangalore) widening progress

An update on the Suranjandas Road:
In the last 2-3 days, pre-cast concrete medians are being installed on the stretch between C V Raman Nagar and Old Madras Road.
Those familiar with this road will know how chaotic the traffic gets, especially in the evenings when many vehicles use the wrong side to move towards the signal quickly.

While this is a good move, what is surprising and worrying are how the lanes are split - the C V Raman Nagar-Old Madras Road side has 1 lane and the other side has 2 lanes. I would have expected this to be reverse since more traffic movement is actually in the single lane side

Lets see how this pans out in the next few days, here's a picture for now:
Suranjan Das Road (Bangalore) widening progress-road-median.jpg
NPV is offline   (2) Thanks Reply With Quote
Reply


Thread Tools Search this Thread
Search this Thread:

Advanced Search


Similar Threads
Thread Thread Starter Forum Replies Last Post
Updates On Nh7 Widening? ramkya1 Route / Travel Queries 8 2nd August 2012 13:20
Sankey road widening..! In whose interest? poloman Shifting gears 22 30th June 2011 14:31
Road widening put on hold... hurray!!! ramki067 Street Experiences 5 16th July 2010 17:06
Stretching and widening of cars in ads. pgsagar The Indian Car Scene 24 14th April 2010 09:13
Parkinson's law of road widening Sawyer Street Experiences 77 28th August 2009 07:30


All times are GMT +5.5. The time now is 13:47.