Quote:
Originally Posted by am1m That is hilarious!
I've read several 'reasons' online for why that particular section is still incomplete. Covid, steel shortage, labour shortage, land acquisition, etc etc. Does anyone know what the actual reason was?
|
Quote:
Originally Posted by am1m Thanks guys, thought it might have something to do with the Railways. Unfortunately, IR seems to always have issues with anything the Metro wants to do, and sorting out anything to do with IR-Metro co-ordination always seems to take much longer than necessary. |
I follow the Namma Metro thread on SkyScraperCity quite closely. So most of what I write here is knowledge gained from there. There are some exemplary individuals who have gone beyond what is humanely possible to bring us regular updates and I will attempt to share some of it here.
The main reason for the delay seems to be the delay in obtaining a line block from SWR (South Western Railway) to move the OWG (Open Web Girder) truss in place over the train tracks. Also there was further delay when SWR officials inspected the OWG and said that bolts on OWG were not torqued as per their specs which again moved the OWG shift by weeks.
Post the OWG being moved, work on the remaining few sections could begin as these were being blocked by temporary support structures for the OWG. The last span till the OWG could be completed once the OWG deck slab had been cast. All sections of this last span have been lifted and stressed. In a few days it will be lowered on the piers.
You can refer to
this post on SSC forum.
Post this the parapet walls, tracks, power and signalling equipment etc need to be completed to link it to Byappanahalli.
Quote:
Originally Posted by airguitar I planned a trip from WFD to Cubbon Park for the Bangalore Habba and was shocked to be told at the counter that the train terminates at Krishnarajapura. No where was it clear that the connectivity to Byappanahalli wasn't done. As it is, I still can't digest the fact that the most blocked/trafficky areas ( including when the govt knew that all/most IT companies were relocating to ORR over the last few years ), ORR and WFD, would get metros 12 years after the initial inauguration ( 14 years perhaps for ORR when it is opened ). Same thing happens on where B-TRACK, or traffic offense monitoring cameras, white topping/quality of roads round the year etc get done. Old bangalore areas always get priority.
Not clear where the metro has to cross over the railwayline : are you referring to the one Bangalore - Hosur rail line at Benniganahalli ?
Also, as far as the overall picture goes : https://themetrorailguy.com/2022/03/...phase-3-plans/ : why is this already looking so messy ? is there a method to the phased madness here that I'm missing ? Feels like random criscrossing of metro routes. |
Till the link between Byappanahalli and KR Pura is completed, BMRCL along with BMTC has feeder bus services between these two stations. You can get down at any station and take a direct bus to the other station and continue the journey. Its not the best solution but its temporary to reduce commuter inconvenience.
Metro alignments are planned years and years in advance since there are various hurdles that need to be overcome before construction can even start. Tasks such as Land Aquisition (and all its associated legal and political hurdles), Environmental clearences, utility shifting, station location planning, tender awarding etc take lot of time. So DPRs need to be able to predict the ROI on an alignment which means predicting future population and traffic. The Whitefield extension work began in 2017 and is coming to a conclusion now. Considering its almost 15km long, it wasn't really quick but wasn't too bad considering all circumstances.
Quote:
Originally Posted by srvm GMaps in satellite view shows that the Purple line metro never crosses the Chennai-Bangalore railway line between Baiyappanahalli and KR Puram. Metro line stays south of the railway line.
However, metro does cross Baiyappanahalli/Banaswadi-Hosur railway line near Baiyappanahalli Auxiliary Bypass cabin. |
Quote:
Originally Posted by Rajeevraj Yes, it crosses over the Baiyappanahalli - Hosur line. And unfortunately the same thing awaits the ORR line also. The ORR Metro line crosses the Hosur Railway line at the Rainbow Hospital area after Marathahalli. If you notice, the spans before and after it are almost ready, but there is nothing happening on both sides of the railway track that goes over the ORR. There was one article that said this is also getting into a loop with railways asking to change design etc as the Hosur line is getting doubled and there is also the proposal of suburban rail. So the metro span should go over 4 tracks out of which today only one is there and the design was planned around covering 2 lines. |
Quote:
Originally Posted by audioholic As usual the bureaucratic mess with railways exist and they seem to be going safe and demanding space for four tracks to pass through(which is another unrealistic expectation) That means another open web girder which on the ORR is impossible to launch without shutting down the entire ORR. |
This is a concern really. SWR has again thrown a spanner in the works by asking for change in the design. It was planned for an OWG already but now SWR wants space for more tracks (whether the space is actually avilable is debatable) which means a longer OWG. Thus not only the current OWG being manufactured has to be modified, but the pier locations design will also change because this line uses precast U-girders which cannot be shortened/lengthened at will. This would mean changing the design of piers or worse relocating them and chaging their design to accomodate composite girders. All this would require new planning, soil testing, utility shifting if necessary and new piling for new piers. All in a narrow space with minimal impact on traffic flow. This alone has the potential to set back this line by months. Then there is another OWG for the blue line depot entrance track to cross the Hosur line at Beninganahalli which again will bring unknown set of challenges.
Quote:
Originally Posted by Rajeevraj Hope you are proven wrong, but I agree with you. The station work is not really started anywhere and as you rightly said, structure completion can be done very fast. The only plus point is that until now, in all other sections, the structure work itself was painfully slow. On ORR at least that part has been taken care off. 2026-27 is my estimate too.
Not sure if they can prioritize 3-4 stations and get the line running as the 2 ends will anyway be ready. I recall Dubai Metro used to follow that approach. They opened lines with few stations ready and then kept adding as it got done. |
Quote:
Originally Posted by audioholic In addition to the structural works, what is also important is the availability of depots and rolling stock. For the ORR metro, it would use the Baiyyapanahalli depot which will be remodelled to suit its needs while the existing rakes for purple line will be shifted to Kadugodi Depot. If so, then the line shall be ready to use at least from KR Pura till Rainbow hospital.
For the Yellow line, provided rolling stock and depot is ready soon, we can see operations until Udupi garden by next year for sure. Its only Jayadeva hospital exchange that will be a blocker. But that anyway is almost the end of the line and people could make use of this line between Silk board and Bommasandra.
|
Opening a line in sections while sounds easy in principle, will need advance planning since you need a crossover track for trains to reverse and shift to the opposite track. This crossover track has to be precisely after the station being opened for optimal operations. With U-girders this cannot be done as they are enclosed by design and you cannot create an opening between adjacent U-girders for a crossover track. A crossover track requires a composite girder which requires a different pillar/pier structure
Then comes the availability of trainsets. I think for Yellow line the trainsets were to be delivered by CRRC of China who was required to setup a plant in India. This was before the Galwan clash post which CRRC's plan of setting up local assembly was abandoned. Now they have entered into a JV with an Indian company, Titagarh Wagons Ltd., who are setting up a factory in WB. But it'll still be a while before they start delivery of trainsets. All other manufacturers of trains such as BEML, Alstom etc already have their orderbooks full with Metros coming up in various cities in India.
So while BMRCL is not best, we have to appreciate the challenges behind massive projects such as these and accept that there will be delays. In some case the contractors are making very good progress especially on the Blue line but such projects can slow down for various reasons.
What is good though is the interest in such projects among the general public which means its better for govts in the long run to see them completed.
While I see the challenges I havent lost hope that we will soon see more metro lines coming up!